NR613 Design Tutorial
Interactive guideline walkthrough for bonded joint design under NR613 rules
Interactive tutorial: bonded joint design according to NR613
Standalone · client-side · English
Objective
This tutorial guides a step-by-step design of a structural bonded joint in accordance with NR613 (Bonded Assemblies). It includes scope definition, selection of justification method (A/B/C), safety factor checks, test requirements, manufacturing control (MTI Bonding Plan), and surface preparation.
The guidance excerpts follow the provided NR613. Use this tutorial as an interactive checklist; final decisions and submissions must comply with the applicable Classification Society requirements.
Fluxo resumido (Passo a passo)
1. Define scope & safety class (SC)
Describe function, onboard location, loads, and environmental conditions. (NR613 - methodology and specification).
2. Determine maturity & qualification level Q
Choose Q1–Q5 based on design maturity and safety. (NR613 - requirements table).
3. Prepare Bonding Specification & Design File
Drawings, planned adhesive thickness(es), processes, surface preparation, and acceptance criteria.
4. Select justification method
Method A (tests), B (analysis), C (analysis + tests). Each has specific requirements and factors.
5. Plan testing and MTI Bonding Plan
Assemble manufacturing plan, tests (characterization/aging/fatigue per Q), and traceability.
6. Production, NDT inspection and validation
Perform environmental controls, final checks, NDT, and document for submission.
Fonte: NR613 - Sec 2 e Sec 5.
Joint design — practical recommendations
NR613 key design considerations:
Surface preparation (summary)
- Cleaning and degreasing;
- Substrate-appropriate abrasion (sand, grit, bristle, etc.);
- Final cleaning; apply primer if recommended by the manufacturer;
- Record batch numbers of materials used and adhesion test results.
Verification methods cited in NR613: wettability measurement (NF EN 828), wetting tension (ASTM D2578), and pull-off testing.
Testing and characterization
Typical test selection (per Q and method):
MTI Bonding Plan — key points
The MTI Bonding Plan should cover adhesive purchase and storage through application, cure, NDT and traceability (batches, temperature, humidity, time between operations).
- List of materials and tools;
- Storage control and shelf life;
- Mixing/dosing procedures and pot-life;
- Environmental controls during application;
- Acceptance criteria and record sheet.
Export / copy checklist
You can copy the checklist below:
References (NR613 excerpts used)
- Methodology and evaluation stages: NR613 Sec 2.
- MTI Bonding Plan — content and requirements: NR613 Sec 5 and Appendix 6.
- Surface preparation — cleaning, abrasion, wettability tests: NR613 Sec 5 (4.3.2) and App 7.
- Justification methods: Method A, B, C and requirements (2.2–2.4).
- Safety factors and formula (SF ≥ α·Ct·Cv·CF·Cθ·Cb): NR613 Sec 3.
- Testing and characterization (Tg, moduli, DCB/ENF/TAST/SLJ...): NR613 Sec 3 and App 4.
Use these references when submitting documentation to the Classification Society.